Grading, drainage and ground prep is mostly complete... slab's poured for the main store building... some curbing is in... slab is formed for the processing area - should pour it this week. There's still a lot of work to do.... scale foundation/installation, double fencing, buildings, paving, plumbing, electrical, equipment purchase and installation, etc, etc. I hope to start buying cars around June 15th with a temporary container office and wireless laptop until the building's complete..... a soft opening is planned for about August 15th if all goes on schedule.... we'll see.